The Carbon Cost of Building the Future: Why Capital Projects Need Their Own Carbon Accounts

construction carbon reporting

Across the UK, enormous amounts of capital are being invested in new infrastructure. Electricity networks are being reinforced and expanded, water companies are investing in treatment works and network resilience, rail infrastructure continues to be renewed, and the growth of data centres is driving major new construction and energy infrastructure projects. Alongside this, businesses continue to invest in factories, warehouses, offices, renewable energy systems and new production equipment.

We tend to think about these projects in terms of what the completed asset will achieve. A new substation increases electricity network capacity, a new treatment works improves water infrastructure, a new railway project increases transport capacity, and a new data centre provides additional digital infrastructure. However, before any of these assets can operate, they have to be built – and building them can create a very significant carbon footprint.

For some organisations undertaking major capital programmes, the emissions associated with constructing new assets could potentially be greater than the emissions generated from their normal operations during the same period. That creates an important question: are we measuring the carbon footprint of our capital projects with anything like the same discipline with which we measure their financial cost?

Capital purchases are Scope 3 emissions

Under the GHG Protocol, capital goods are reported within Scope 3 Category 2. The category covers the upstream, cradle-to-gate emissions associated with capital goods purchased or acquired by the reporting organisation.

For a major construction project, this can mean enormous quantities of concrete, cement, reinforcing steel, structural steel, asphalt, aggregates, pipework, cabling, electrical equipment, transformers, switchgear, mechanical equipment, process equipment and manufactured components.

However, understanding and reducing the carbon associated with delivering the project requires visibility of more than just the materials incorporated into the finished asset. Construction also involves excavators, cranes, generators, compressors, piling rigs, temporary buildings, site electricity, diesel, transport, waste and numerous subcontractors.

The principle should therefore be relatively simple: a major construction project should have its own carbon account.

The principal contractor is in the best position to build that carbon account

We already expect principal contractors to manage enormous quantities of project information. They manage cost, programme, labour, health and safety, quality, materials, plant, subcontractors and waste. Carbon should increasingly become another normal project metric.

The principal contractor should record the relevant activity data as the project progresses rather than attempting to reconstruct the project’s carbon footprint at the end. This means capturing information such as material quantities, fuel consumption, temporary electricity consumption, plant and machinery activity, transport, waste and other significant project activities.

The objective should be to produce a robust carbon account for the completed capital asset. The contractor records the activity, the carbon calculation converts that activity into emissions, and the client ultimately receives both the physical asset and the information required to understand the carbon footprint associated with acquiring it.

This is much more useful than simply receiving a figure at handover stating that the project produced, for example, 18,500 tonnes CO2e. The client should be able to understand what created those emissions. Perhaps 45% came from concrete and cement, 25% from steel, 10% from other materials and the remainder from construction energy, transport, plant, waste and other activities. Once that breakdown becomes visible, carbon becomes something that can actually be managed.

Carbon needs to be managed during construction, not calculated afterwards

This is perhaps the biggest opportunity. If the carbon footprint is calculated six months after a project has been completed, the number might be useful for corporate reporting, but it is largely useless for reducing the carbon footprint of that particular project.

By then the concrete has been poured, the steel has been installed, the excavators have burned the diesel and the waste has left the site. The opportunity to make different decisions has gone.

Carbon therefore needs to be visible while design, procurement and construction decisions can still be changed. Could lower-carbon concrete be specified? Could recycled or lower-carbon steel be used? Could excavation material be reused on site? Could deliveries be consolidated? Could electric construction plant replace diesel equipment? Could temporary site power come from the electricity network rather than diesel generators? Could construction waste be reduced? Could equipment and materials be sourced closer to the project? Could a design change reduce the quantity of material required in the first place?

Many of these decisions can affect both carbon and cost. A carbon reduction plan should therefore sit inside the main capital project rather than being something produced after the project has been completed.

Carbon should become part of the tender evaluation

This approach needs to start before the contractor arrives on site. When a client evaluates bids for a major capital project, the assessment will normally consider price, technical capability, experience, programme, quality, health and safety and commercial risk.

I believe carbon management increasingly needs to become another scored element of that tender.

The question should not simply be: “Does your company have a net-zero target?” It should be: “How will you measure, manage and minimise the carbon footprint of our project?”

Tenderers could be required to demonstrate:

  • How project carbon data will be collected and reported.
  • Which materials and activities will be measured.
  • How subcontractor and supplier information will be captured.
  • How fuel, electricity, plant and machinery energy consumption will be recorded.
  • How embodied carbon will influence procurement and design decisions.
  • How carbon reduction opportunities will be identified and evaluated.
  • What project carbon information will be provided to the client during construction and at handover.

This moves carbon away from being a sustainability questionnaire completed during procurement and makes it part of actual project delivery.

The lowest-price project may not necessarily be the lowest-carbon project. Equally, the lower-carbon option does not necessarily have to be more expensive. Reducing material quantities, fuel consumption, transport movements and waste can reduce both carbon and project costs.

What happens when a project lasts several years?

Many major infrastructure projects run across several financial and carbon reporting years. This creates an important reporting consideration for the client: how and when should the emissions associated with the capital asset be recognised within its carbon reporting?

An organisation may choose an approach that reflects the project emissions progressively as construction takes place, or its methodology may result in the completed capital purchase being recognised at another defined point. Whichever approach is adopted, consistency and transparency are essential.

A major capital programme cannot effectively disappear from carbon management for several years and then unexpectedly emerge as a huge Scope 3 figure without explanation. Tracking the carbon at project level provides the information required to understand what is happening throughout construction, even where the client’s eventual corporate reporting treatment is different.

It also allows the organisation to distinguish between changes in operational performance and changes caused by capital investment.

Imagine, for example, a utility whose normal annual operational carbon footprint is 80,000 tonnes CO2e. It then undertakes a major infrastructure programme associated with another 120,000 tonnes CO2e of capital emissions. The organisation’s total reported footprint could increase dramatically, even while its underlying operational efficiency is improving.

Has the organisation suddenly become less carbon efficient? Not necessarily. It may actually be investing in infrastructure that will reduce operational emissions or improve efficiency over the following 20 or 30 years.

That distinction needs to be understood and communicated. A sufficiently large capital programme may even require an organisation to reconsider how it presents its carbon baseline, targets and reduction trajectory so that changes caused by investment are visible rather than being confused with changes in operational performance.

But don’t let the big number hide all the smaller opportunities

There is another risk when capital carbon becomes a dominant part of the footprint. Everything else can suddenly look insignificant.

If a major infrastructure programme generates 100,000 tonnes CO2e, employee commuting of 2,000 tonnes, customer travel of 500 tonnes, business travel of 300 tonnes and waste of 200 tonnes can start to look almost irrelevant.

They are not.

A business may have relatively little ability to eliminate the embodied carbon of thousands of tonnes of essential infrastructure materials immediately. It may, however, be able to reduce employee commuting emissions this year. It may be able to reduce business travel, improve waste segregation, reduce electricity consumption, change procurement practices or work with suppliers to reduce emissions.

Carbon management therefore needs two perspectives at the same time: manage the largest sources of emissions while continuing to pursue the reductions that are achievable.

Otherwise, a huge construction programme can unintentionally become a reason for ignoring dozens of smaller opportunities where the business has much greater control and where carbon savings may be considerably easier to achieve.

We need project carbon accounts

I think major capital projects increasingly need to be treated almost like temporary businesses for carbon management purposes. Give the project an identity, establish its reporting boundary and then record its materials, energy, fuels, plant, waste, transport and suppliers throughout the construction period.

The project should also have its own carbon reduction plan. Opportunities should be identified, assigned, evaluated and tracked in much the same way as other project actions. Carbon performance can then be reviewed alongside cost, programme, quality and safety.

At the end of the project, the client receives more than an asset and a final carbon estimate. It receives a structured record explaining the carbon associated with constructing that asset, how that footprint developed throughout the project and what was done to reduce it.

This is where CO2 Impact can help

CO2 Impact has been designed around recording operational activity and converting that activity into structured Scope 1, Scope 2 and Scope 3 carbon information. The same multi-site structure provides a practical approach for organisations wanting to manage multiple capital projects.

A large utility or infrastructure organisation could establish individual construction projects within its reporting structure and use CO2 Impact to capture and monitor the underlying activity data. Instead of receiving one carbon figure at handover, the client can build a structured carbon record throughout the life of the project.

For organisations running multiple projects simultaneously, this becomes particularly valuable. Individual projects can be monitored separately while their emissions can also be considered within the organisation’s wider carbon footprint. Projects lasting several years can retain their own history, allowing the organisation to understand when emissions occurred and what caused them.

More importantly, carbon reduction opportunities can be identified and tracked within the projects themselves. The objective is therefore not simply better carbon reporting. It is better carbon management.

We already expect a principal contractor to tell us what a project cost, how safely it was delivered, whether it was completed on time and whether it met the required technical specification.

For a major capital project, perhaps we should also expect them to tell us, accurately and transparently, what it cost in carbon.

And the most important question should not be asked at handover.

It should be asked throughout the project:

What are we doing now to make that carbon number smaller?

#CarbonAccounting #Scope3 #CapitalCarbon #EmbodiedCarbon #Construction #Infrastructure #CarbonReduction #NetZero #SECR #CO2Impact

Measure - Manage - Reduce - Offset - Report

Bryce Energy Services combines practical energy and carbon consultancy with the CO₂ Impact online platform, helping businesses measure their emissions, meet reporting requirements and turn carbon data into achievable reduction projects.

With CO₂ Impact, your business can:

  1. Calculate Scope 1, 2 and 3 emissions
  2. Produce credible carbon reports and Carbon Reduction Plans
  3. Monitor energy, emissions and progress year by year
  4. Identify and manage practical carbon-reduction projects
  5. Build an evidence-based route towards net zero

Unlike a standalone carbon calculator, we can help you interpret the results, investigate energy-saving opportunities and prioritise projects based on cost, carbon savings and practical deliverability.

CO2 Impact
CO2 Impact Online Carbon Tool

CO₂ Impact subscriptions start from £29 per month.

Go to Registration CO2 Impact site Demo video on YouTube
This site uses cookies to offer you a better browsing experience. By browsing this website, you agree to our use of cookies.